Quick Points

Partial demolition of a multi-level parkade structure and connecting +15 walkway
Complete demolition of the +30 walkway connected to the parkade
Completed during three-hour, early-morning sessions coinciding with regularly scheduled C-train maintenance schedule

Project Additional Body Rendered

Breaking down demolition challenges

The project involved the removal of two elevated walkways above the light-rail transit lines in Calgary’s downtown core, which restricted the demolition to short periods of time coinciding with the early morning, off-hours line service maintenance schedule. The Bluebird demolition team developed a unique and innovative solution, specific to the project requirements, to ensure the demolition was completed safely and with minimal disruption to Calgary’s transit services.

Project Additional Body Rendered

Project Additional Body Rendered

Brookfield Place East

Breaking down demolition challenges

The project involved the removal of two elevated walkways above the light-rail transit lines in Calgary’s downtown core, which restricted the demolition to short periods of time coinciding with the early morning, off-hours line service maintenance schedule. The Bluebird demolition team developed a unique and innovative solution, specific to the project requirements, to ensure the demolition was completed safely and with minimal disruption to Calgary’s transit services.

Market: 
Service Type: 
Location: 
Calgary
Province or State: 
Alberta
Country: 
Quick Points: 
Partial demolition of a multi-level parkade structure and connecting +15 walkway
Complete demolition of the +30 walkway connected to the parkade
Completed during three-hour, early-morning sessions coinciding with regularly scheduled C-train maintenance schedule
Project Asset: 
Gallery Media: 
Bluebird Demolition at Brookfield Place East
Bluebird Demolition at Brookfield Place East
Bluebird Demolition at Brookfield Place East
Thumbnail: 
Bluebird Demolition at Brookfield Place East
Start / End: 
January 2015