To complete this project in 12 days, most work was done 24/7
With over 10,000 man-hours on this project, T&M had zero lost-time incidents

Project Additional Body Rendered

Come Hell or High Water: Rebuilding a Calgary Legacy

The flood cleanup project consisted of complete removal and reinstatement of the track, bank rehabilitation and protection, bridge demolition, de-watering and rehab work to the Big 4 building, and asphalt patching.

Project Additional Body Rendered

Project Additional Body Rendered

Calgary Stampede Flood Cleanup

Come Hell or High Water: Rebuilding a Calgary Legacy

The flood cleanup project consisted of complete removal and reinstatement of the track, bank rehabilitation and protection, bridge demolition, de-watering and rehab work to the Big 4 building, and asphalt patching.

Market: 
Location: 
Calgary
Province or State: 
Alberta
Country: 
Quick Points: 
To complete this project in 12 days, most work was done 24/7
With over 10,000 man-hours on this project, T&M had zero lost-time incidents