Centec is actively managing 28 projects at Koch Fertilizer as part of the Pre-TA Preparation and Plant Turnaround in 2025, with project values ranging from $4,000 to $800,000.
These projects involve extensive use of Centec equipment on-site, including lifts and zoom booms, to support operations efficiently. The majority of the work is scheduled for completion during the 55-day shutdown event in September 2025, ensuring critical upgrades and maintenance are completed within the planned timeframe.