Line 3 Replacement

Location: Hardisty, Alberta
Year Completed: 2019
Building Trust With Every Job

Project Specifications

Company
whaler industrial contracting
Contract:
$15M+
Contract Type:
Lump Sum
Scope:
civil, fabrication, general, mechanical, structural
Sector:
industrial
Markets:
mechanical, process facility
Client:
Enbridge
Experience Is The Best Teacher

Project Details

This terminal expansion in Hardisty, Alberta was part of the Line 3 Replacement Project and consisted of the supply and installation of a new Meter Manifold which was comprised of four separate modules.

Whaler installed a new Meter Prover, 36” Inlet Manifold, one MCC and two other buildings. There was a total of (450m of 36”) underground piping and (450m of 36” and 350m of 24”) rack piping installed on the project.

Whaler worked in collaboration with Rambler Fabrication to safely complete this project on time and on budget while working in an operational facility.