Syncrude Tailings Relocation

Location: Calgary, Alberta
Year Completed: 2013
Building Trust With Every Job

Project Specifications

Company
rambler fabrication
Contract:
$5M+
Scope:
fabrication, mechanical, structural
Sector:
industrial
Markets:
mechanical
Client:
Cosyn Technologies
Experience Is The Best Teacher

Project Details

Rambler Fabrication's largest project to date was working directly with Cosyn Technologies, fabricating various drop-out spools, nipple pipe and structural anchors for Syncrude Tailings Relocation. Starting with a mill order of pipe, and spanning a time of 10 months, this project included over 85000 diameter inches and was supplied on time and on budget.